Brennans Road Riverbank Restoration, Qld
Following a slip failure approximately 80 metres long along the McIntyre River near Goondiwindi, urgent stabilisation works were required to protect nearby properties and prevent further erosion. The project involved excavating the failed material, constructing a piling platform, and installing sheet piles and a rock mattress to reinforce the riverbank.
Project Scope:
56 sheet piles (12m long)
Project Value:
Approximately $1,200,000
Equipment:
SR60 Piling Rig
M12000 Crane
ICE55NF Vibrator
Working in collaboration with Everest Civil, Caporn Piling successfully delivered this critical riverbank restoration, ensuring long-term stability and erosion protection for the affected area.
Following a slip failure approximately 80 metres long along the McIntyre River near Goondiwindi, urgent stabilisation works were required to protect nearby properties and prevent further erosion. The project involved excavating the failed material, constructing a piling platform, and installing sheet piles and a rock mattress to reinforce the riverbank.
Project Scope:
56 sheet piles (12m long)
Project Value:
Approximately $1,200,000
Equipment:
SR60 Piling Rig
M12000 Crane
ICE55NF Vibrator
Working in collaboration with Everest Civil, Caporn Piling successfully delivered this critical riverbank restoration, ensuring long-term stability and erosion protection for the affected area.