Burnside Village Shopping Centre – Stage 6, SA
Caporn Piling is proud to support the Stage 6 development of the iconic Burnside Village Shopping Centre in South Australia. This expansion project includes the construction of 18,500m² of additional floor space and two basement car park levels, providing enhanced amenities for shoppers and the local community.
Project Scope
Installation of:
1,203 CFA piles (600mm, 750mm, and 900mm diameter, up to 19m deep) for a soldier pile retaining wall.
110 temporary anchors ranging from 15m to 20m in length for structural stability.
9 CFA piles (600mm and 900mm diameter, up to 17m deep) for foundation support.
Equipment Utilized
Bauer BG28 piling rig for efficient CFA pile installation.
Track-mounted concrete pump for seamless concrete delivery.
Soilmec SM14 for precision anchor installation.
Client
McMahon Services
Project Highlights
Delivery of extensive CFA piling solutions for the basement retaining wall and foundation structure.
Installation of temporary anchors to ensure structural stability during excavation and construction.
Execution in a congested urban environment, requiring precise planning and innovative construction methods.
Caporn Piling is proud to support the Stage 6 development of the iconic Burnside Village Shopping Centre in South Australia. This expansion project includes the construction of 18,500m² of additional floor space and two basement car park levels, providing enhanced amenities for shoppers and the local community.
Project Scope
Installation of:
1,203 CFA piles (600mm, 750mm, and 900mm diameter, up to 19m deep) for a soldier pile retaining wall.
110 temporary anchors ranging from 15m to 20m in length for structural stability.
9 CFA piles (600mm and 900mm diameter, up to 17m deep) for foundation support.
Equipment Utilized
Bauer BG28 piling rig for efficient CFA pile installation.
Track-mounted concrete pump for seamless concrete delivery.
Soilmec SM14 for precision anchor installation.
Client
McMahon Services
Project Highlights
Delivery of extensive CFA piling solutions for the basement retaining wall and foundation structure.
Installation of temporary anchors to ensure structural stability during excavation and construction.
Execution in a congested urban environment, requiring precise planning and innovative construction methods.