Cemetery Road Landfill Gas Cut-Off Wall – Upper Kedron Reserve, QLD
Caporn Piling successfully delivered the construction of a landfill gas cut-off wall at Brisbane City Council’s former Cemetery Road Landfill site, now transformed into the Upper Kedron Reserve. This essential project utilized vinyl sheet pile wall methods to effectively manage landfill gas emissions, ensuring environmental protection and community safety.
Project Scope
Excavation of 175 lineal metres of 3m deep bentonite slurry trench for gas containment.
Installation of 175 lineal metres of SG425 vinyl sheet piles up to 10 metres in length, providing a secure gas cut-off barrier.
Application of Adeka A50N sealant to ensure a watertight and gas-impermeable seal.
Equipment Utilised
Bauer RG16 rig for efficient and precise vinyl sheet pile installation.
Client
Epoca Constructions
Project Outcomes
The landfill gas cut-off wall delivered critical environmental benefits, including:
Effective containment of landfill gas emissions to protect nearby land and communities.
Transformation of a former landfill site into a safe, sustainable green reserve for public use.
Implementation of innovative solutions to meet environmental compliance standards.
At Caporn Piling, we are proud to contribute to environmentally responsible projects, delivering innovative piling and gas management solutions that transform legacy sites into valuable community assets.
Caporn Piling successfully delivered the construction of a landfill gas cut-off wall at Brisbane City Council’s former Cemetery Road Landfill site, now transformed into the Upper Kedron Reserve. This essential project utilized vinyl sheet pile wall methods to effectively manage landfill gas emissions, ensuring environmental protection and community safety.
Project Scope
Excavation of 175 lineal metres of 3m deep bentonite slurry trench for gas containment.
Installation of 175 lineal metres of SG425 vinyl sheet piles up to 10 metres in length, providing a secure gas cut-off barrier.
Application of Adeka A50N sealant to ensure a watertight and gas-impermeable seal.
Equipment Utilised
Bauer RG16 rig for efficient and precise vinyl sheet pile installation.
Client
Epoca Constructions
Project Outcomes
The landfill gas cut-off wall delivered critical environmental benefits, including:
Effective containment of landfill gas emissions to protect nearby land and communities.
Transformation of a former landfill site into a safe, sustainable green reserve for public use.
Implementation of innovative solutions to meet environmental compliance standards.
At Caporn Piling, we are proud to contribute to environmentally responsible projects, delivering innovative piling and gas management solutions that transform legacy sites into valuable community assets.