0
Skip to Content
Caporn Piling
Home
What We Do
Bored Piling
CFA Piling
Design & Construct
Driven Concrete Piling
Down the Hole Hammer
Driven Steel Tubular Piling
Ground Improvement
Marine Piling
Retaining Walls
Specialist Applications
Support Fluids
Temp. Access Bridges
Equipment
Projects
Who We Are
Our History
Our Team
Our Strategy
Careers
Contact
Queensland Head Office
Queensland Gold Coast
New South Wales
South Australia
Caporn Piling
Home
What We Do
Bored Piling
CFA Piling
Design & Construct
Driven Concrete Piling
Down the Hole Hammer
Driven Steel Tubular Piling
Ground Improvement
Marine Piling
Retaining Walls
Specialist Applications
Support Fluids
Temp. Access Bridges
Equipment
Projects
Who We Are
Our History
Our Team
Our Strategy
Careers
Contact
Queensland Head Office
Queensland Gold Coast
New South Wales
South Australia
Home
Folder: What We Do
Back
Bored Piling
CFA Piling
Design & Construct
Driven Concrete Piling
Down the Hole Hammer
Driven Steel Tubular Piling
Ground Improvement
Marine Piling
Retaining Walls
Specialist Applications
Support Fluids
Temp. Access Bridges
Equipment
Projects
Folder: Who We Are
Back
Our History
Our Team
Our Strategy
Careers
Folder: Contact
Back
Queensland Head Office
Queensland Gold Coast
New South Wales
South Australia
Caporn-4.jpg
Waratah Crew.jpg
Waratah 1.jpg
Waratah 2.jpg

Waratah Super Battery, NSW

$0.00

The Waratah Super Battery Project is a landmark energy infrastructure development designed to enhance grid stability and support renewable energy integration in New South Wales. As part of this initiative, Caporn Piling was engaged to construct transmission pole foundations essential for the project’s high-capacity energy storage system.

Project Scope:

  • 12 transmission pole foundations across 6 sites

  • Utilisation of bored piles and anchors for structural stability

Project Value:

  • Approximately $5,400,000

Equipment:

  • BG24H

  • BG28H

  • Soilmec SM401-077A

  • 12t excavator

  • Crane Truck

  • Skid Steer

Partnering with Zinfra Pty Ltd, Caporn Piling played a critical role in supporting this cutting-edge energy infrastructure, reinforcing the future of renewable energy storage in New South Wales.

Projects Waratah Super Battery, NSW
Quantity:
Add To Cart

The Waratah Super Battery Project is a landmark energy infrastructure development designed to enhance grid stability and support renewable energy integration in New South Wales. As part of this initiative, Caporn Piling was engaged to construct transmission pole foundations essential for the project’s high-capacity energy storage system.

Project Scope:

  • 12 transmission pole foundations across 6 sites

  • Utilisation of bored piles and anchors for structural stability

Project Value:

  • Approximately $5,400,000

Equipment:

  • BG24H

  • BG28H

  • Soilmec SM401-077A

  • 12t excavator

  • Crane Truck

  • Skid Steer

Partnering with Zinfra Pty Ltd, Caporn Piling played a critical role in supporting this cutting-edge energy infrastructure, reinforcing the future of renewable energy storage in New South Wales.

Projects Waratah Super Battery, NSW

Expert Piling Solutions Start Here – Request a Quote Now

Contact Us for Expert Piling Advice
Name *

Thanks for your enquiry.
Our expert team will be in touch shortly.

Queensland Head Office

139-169 Potassium Street
Narangba, QLD 4504
P: +61 7 3889 3989
E: admin@capornpiling.com.au

Queensland Gold Coast

18/240 Varsity Parade
Varsity Lakes, Qld 4227
P: +61 7 38893989
E: admin@capornpiling.com.au

New South Wales Office

30-32 Barcoo Street
Roseville, NSW 2069
P: +61 2 9882 3817
E: admin@capornpiling.com.au

South Australia Office

22 Greenhill Road
Wayville, SA 5034
P: +61 8 8372 7808
E: admin@capornpiling.com.au


Featured Projects
Bored Piles
CFA Piles
Design & Construct
Marine Piles

Driven Concrete Piles
Down the Hole Hammer
Driven Steel Tubular Piles
Retaining Walls
Ground Improvement

Specialist Applications
Support Fluids
Temporary Access Bridges
FAQ’s

Copyright © 2025 Caporn Piling